po-split-story

Applies proven story splitting patterns to break an oversized user story or epic into sprint-sized, independently deliverable stories. Use when a Product Owner or developer says things like "this story is too big", "we need to split this", "this will not fit in a sprint", "break this epic down", "help me slice this story", or when a story fails the Small criterion in INVEST. Do not use for writing new stories from scratch — use po-create-user-story instead. Do not use for sprint planning or backlog prioritization.

stable

Contents

Story Splitting

Purpose

A story that cannot fit in one Sprint is a planning liability — it blocks commitment, obscures progress, and almost always hides scope nobody agreed to. This skill applies the nine proven splitting patterns to turn one large story into multiple small ones, each independently valuable and completable in a single Sprint.


Tool detection

  1. Check for active mcp__azure-devops__* tools → $PM_TOOL = ado
  2. Check for active mcp__jira__* tools → $PM_TOOL = jira
  3. If both → ask which tool to use
  4. If neither → $PM_TOOL = manual

Step 1 — Fetch the story

Ask: "Which story needs splitting? Provide the ID or paste the content."

  • ADO: use wit_get_work_item — read title, description, acceptance criteria, story points, and parent
  • Jira: use the get-issue tool — read summary, description, acceptance criteria, story points, and epic link
  • Manual: accept pasted content

If the item is an Epic, treat the whole Epic as the input. Store as $STORY.


Step 2 — Diagnose why it is too large

Before splitting, understand what makes it large. This determines which pattern fits best.

Ask yourself — and the PO if needed:

  • Does it cover multiple user types? → split by persona
  • Does it span multiple workflow steps end-to-end? → split by workflow
  • Does it handle many data variations or edge cases? → split by data
  • Does it cover both the happy path and error handling? → split happy/unhappy
  • Does it need to work across multiple channels (web, mobile, API)? → split by interface
  • Does it include both basic and high-performance versions? → split by performance
  • Does it bundle create, read, update, delete? → split by operation (CRUD)
  • Does it mix a core feature with validation, logging, or notifications? → split cross-cutting concerns
  • Does it depend on a system integration that is not ready? → defer the integration, stub it first

Step 3 — Apply the best-fit pattern

Pattern 1 — Workflow steps

Split the story at each step in the user's journey. Each step becomes its own story.

Original: As a manager, I want to approve expense claims end-to-end.

Split:
→ Submit an expense claim for approval
→ Review pending expense claims as a manager
→ Approve or reject an individual claim
→ Receive a decision notification as a claimant

Pattern 2 — Business rule variations

Keep the happy path in one story. Each significant business rule variation becomes its own story.

Original: Apply discount rules to an order at checkout.

Split:
→ Apply a fixed percentage discount code at checkout
→ Apply a tiered loyalty discount based on account history
→ Apply free-shipping thresholds to qualifying orders

Pattern 3 — Happy path / unhappy path

Deliver the working case first. Error handling, edge cases, and validation follow as separate stories.

Original: Export transaction history with full validation.

Split:
→ Export transaction history as CSV for a valid date range [happy path]
→ Show an error when the date range exceeds 12 months [unhappy path]
→ Handle export timeouts gracefully for large datasets [edge case]

Pattern 4 — Data variations

Same operation, different data types or states.

Original: Manage all document types in the file library.

Split:
→ Upload and preview PDF documents
→ Upload and preview image files
→ Upload and preview spreadsheets

Pattern 5 — Interface / channel

Deliver one channel first. Other channels follow as separate stories.

Original: Receive low-balance alerts across all channels.

Split:
→ Receive low-balance alerts via email
→ Receive low-balance alerts via push notification
→ Receive low-balance alerts via SMS

Pattern 6 — Operations (CRUD)

Split by create, read, update, delete. Read is usually the most valuable starting point.

Original: Manage team members.

Split:
→ View the list of current team members [Read]
→ Add a new team member [Create]
→ Update a team member's role [Update]
→ Remove a team member [Delete]

Pattern 7 — Performance

Deliver basic functionality first. Optimised performance is a separate story.

Original: Generate the annual report with real-time data.

Split:
→ Generate the annual report from cached data [basic]
→ Generate the annual report with real-time refresh [optimised]

Pattern 8 — Deferred system integration

Replace the integration with a manual or stub step. Automate it as a follow-up story.

Original: Sync approved claims to the accounting system automatically.

Split:
→ Export approved claims as a CSV for manual upload to accounting [stub]
→ Sync approved claims to the accounting system via API [automation]

Pattern 9 — Cross-cutting concerns

Deliver core functionality first. Add notifications, audit logs, and validation as follow-up stories.

Original: Create a project with full validation, notifications, and audit log.

Split:
→ Create a project with basic required fields
→ Validate project name uniqueness across the organisation
→ Notify project stakeholders when a project is created
→ Log project creation events to the audit trail


Step 4 — Present the split

For each resulting story, produce a complete draft:

Split Story [N] of [total]

Title: [action-oriented title]
As a [specific persona],
I want [concrete action],
so that [measurable benefit].

Acceptance Criteria:
- [ ] [Observable condition]
- [ ] [Observable condition]

Size signal: [Small — fits one Sprint / Medium — verify with team]
Dependency: [None / Depends on Story N being done first]

Then present the full set and ask: "Does this split make sense? Any stories to merge, rename, or reorder before I create them?"


Step 5 — Confirm and create

After confirmation:

  • ADO: create each story as a Product Backlog Item using wit_create_work_item, linked to the original parent Feature or Epic
  • Jira: create each story as a Story linked to the original Epic
  • Optionally mark the original oversized story as Resolved/Closed with a comment: "Split into [#IDs]."

Never create without explicit confirmation.


Guardrails

  • Every split story must be independently valuable — if story N is useless without story N+1, it is not a valid split.
  • Never split by technical layer (frontend story, backend story, database story) — that is task decomposition, not story splitting. A story must deliver user value end-to-end.
  • If a story cannot be split without losing value, say so: "This story is atomic — the value only exists when all parts are present. Consider whether the whole story fits in the Sprint with the current team capacity."
  • Keep the original story's parent link on all split stories — they should all trace back to the same Feature or Epic.

Provenance

Authored by abrahamFerga in abrahamFerga/scrum-skills. The content is mirrored here under its upstream license.

Related

audit-backlog-ado Audits the Azure DevOps product backlog for hygiene, story quality, and refinement readiness — identifying items that are too large, missing acceptance criteria, stale, unestimated, or out of priority order. Use when a Scrum Master or Product Owner says things like "audit the backlog", "is the backlog healthy", "review the backlog before refinement", "clean up the backlog", "check backlog hygiene", or "prepare the backlog for planning". Do not use for individual story audits — use audit-user-story for that. Do not use for sprint planning or velocity review. abrahamFerga/scrum-skills MIT audit-sprint-ado Audits a completed or in-progress Azure DevOps sprint against Scrum and ADO best practices — checks Sprint Goal presence, work item hygiene, state transitions, field completeness, capacity tracking, and Definition of Done compliance. Surfaces findings with severity levels and offers to post a summary to the ADO wiki or add comments to specific work items. Use when anyone says things like "audit our sprint in ADO", "review the sprint in Azure DevOps", "check our ADO sprint health", "are our work items following best practices", or "sprint health check". Don't use for Jira, Sprint Planning, Daily Scrum, or Retrospective. Requires an Azure DevOps MCP connection. abrahamFerga/scrum-skills MIT audit-sprint-jira Audits a completed or in-progress Jira sprint against Scrum and Jira best practices — checks Sprint Goal presence, issue hygiene, workflow transitions, field completeness, story point coverage, and sub-task consistency. Surfaces findings with severity levels and offers to add comments to specific issues or export a summary report. Use when anyone says things like "audit our sprint in Jira", "review the Jira sprint", "check our Jira sprint health", "are our issues following best practices", or "sprint health check in Jira". Don't use for Azure DevOps — use audit-sprint-ado instead. Don't use for Sprint Planning, Daily Scrum, or Retrospective. Requires a Jira MCP connection. abrahamFerga/scrum-skills MIT audit-sprint-retrospective-ado Reads an Azure DevOps retrospective — from the ADO Retrospectives extension board, a wiki page, or retro-tagged work items — and produces a structured summary of what the team said, identifies patterns and recurring themes, audits whether action items are properly tracked as work items with owners, and generates concrete suggestions. Use when anyone says things like "summarize our retro", "audit the retrospective in ADO", "what were the action items from the retro", "review the team's retrospective board", "check our retro follow-up", or "did we capture everything from the retro". Don't use for facilitating a retrospective in real time, Jira projects, or general Scrum questions. abrahamFerga/scrum-skills MIT audit-user-story Audits an existing user story against Scrum best practices — checks INVEST criteria, story format, acceptance criteria quality, and Definition of Ready compliance. Raises findings with clear severity levels and offers to post the audit as a comment on the work item for the Product Owner or PM to act on. Use when anyone says things like "audit this story", "review this user story", "is this story ready", "check this PBI", "does this story meet best practices", or pastes a story and asks for feedback. Don't use for creating new stories, sprint planning, or general Scrum questions. Works with ADO, Jira, or a pasted story. abrahamFerga/scrum-skills MIT